Master Facility Plan
The Master Facility Plan process began in 2014
- The district contracted with Roth|Lesko for a facility assessment.
- The purpose was to determine the cost for necessary renovations and the cost for replacement of our school buildings.
- These were compared to determine a ratio of how much it would cost to renovate a building as compared to replacing it with a new one.
Phase 1: 2015 – 2018
- A bond/levy was for 3 new elementary schools and renovations.
- Taylor Elementary, Struble Elementary, and Pleasant Run Elementary opened and renovations on other buildings are complete.
Phase 2: 2021
- NWLSD community stakeholders began the process of evaluating the next steps in the Master Facility Plan.
- Educational Visioning teams and Community Advisory Teams were formed to evaluate district needs. They will make a recommendation to the Board of Education upon completion.
OCT 2014
Original Master Facility Plan Finalized
NOV 2015
Bond Levy Passed for Elementary Schools and Renovations
NOV 2015
JUNE 2016
Elementary Visioning Begins
AUG 2018
Three Elementary Schools Open & Renovations Completed
AUG 2018
MAY 2021
Community Survey
AUG 12, 2021
Community Forum #1
Master Facility Plan Update
AUG 12, 2021
AUG 18, 2021
Community Advisory Team
Session #1
AUG 25, 2021
Educational Visioning Team
Session #1
AUG 25, 2021
SEPT 1, 2021
Community Advisory Team
Session #2
SEPT 8, 2021
Educational Visioning Team
Session #2
SEPT 8, 2021
SEPT 15, 2021
Community Advisory Team
Session #3
SEPT 22, 2021
Educational Visioning Team
Session #3
SEPT 22, 2021
SEPT 29, 2021
Community Forum #2
Master Facility Plan Update & Survey
OCT 12, 2021
Community Advisory Team
Session #4
OCT 12, 2021
NOV 3, 2021
Community Advisory Team Presentation
Master Facility Plan recommendations to the Board of Education
DEC 2021
Review State Funding Options
Board of Education votes on OFCC funding options
DEC 2021
JAN 2022
State Approves Final Funding Agreements